csom - Set baseline programmatically in project server -


how can set baseline programmatic-ally in microsoft project server? there blogs this?

providing version using or useful details can explain question properly.

but in general cannot set baselines using psi nor csom, according msdn post here: https://msdn.microsoft.com/en-us/library/office/ee767706.aspx?f=255&mspperror=-2147217396#pj14_whatpsidoes_doesnotdo

actions require project professional: following list things neither psi nor csom can do. . . . baselines , earned value

  • saving baseline or editing baseline data.
  • setting progress date.
  • calculating variance , earned value.

Comments

Popular posts from this blog

html - How to set bootstrap input responsive width? -

javascript - Highchart x and y axes data from json -

javascript - Get js console.log as python variable in QWebView pyqt -